Milestones

Progress Milestones

Milestones

Tentative Timelines

2023
Town Planning Board Submission
  • Carry out public consultation activities
  • Conduct feasibility study and all technical assessments
  • Liaise with the Government for land acquisition matters
  • Submit Planning Application to Town Planning Board and obtain its approval
2023
2024 - 2025
Design Stage
  • Start liaison with Lands Department for land grant and lease conditions
  • Appoint architectural and structural consultant and commence statutory submissions to Buildings Department as well as other government departments
  • Commence detail design and establish a detailed cost estimate
  • Manage the final design within budget
2024 - 2025
2025
Tender Stage
  • Incorporate all details, techncial specifications, project-specific requirements into tender documentation
  • Commence pre-qualification process for tenderers
  • Commence tendering process for contract works
2025
2026 - 2028
Construction Stage
  • Appoint Registered Specialist Contractor and Registered General Building Contractor
  • Commence construction works including site formation works, substructure, superstructure, finishing works, landscaping works and footbridge erection etc.
  • Monitor site progress
2026 - 2028
2028
Completion and Operation
  • Commence all statutory inspections with the authorities and obtain Occupation Permit from Buildings Department
  • Move in furniture and equipment
  • Commence testing and commissioning, and operation
2028

Tentative Schedule

Early 2021

 

 

March 2022

 

August 2022 – July 2023

 

Late June 2023

 

September 2023

 

January 2024

 

 

April 2024

 

January 2025

 

June 2025

 

September 2026

 

February 2028

 

April 2028

 

July 2028

Identification of SSS Slope Site as potential new campus

Appointment of consultant to carry out Technical Feasibility Study

 

Appointment of Planning Consultant to prepare Section 16 application to Town Planning Board

 

Public Consultation

 

Submission of pre-circulation documents to Planning Department and Government departments

 

Submission of Formal Application to Town Planning Board

 

Application for Land Grant

Appointment of Architecture Design Consultant

 

Building plan submission

 

Detail Design

 

Foundation Works

 

Superstructure Works

 

Statutory Inspections

 

Testing and Commissioin, and Furniture Move‐in

 

Handover